Company:
Client:
Where:
Libya
When:
2019
Engineering service provided:
Front End Engineering Design (FEED) including the 3D Modelling.
Project Description:
FEED relevant to the offshore development for the Structures “A” and “E” and Sabratha Upgrade. The scenario envisages a dry tree development of both fields. In in particular: a Wellhead Platform (WHPA) located on A field and a Production Platform (PPE) located on E field with five subsea wells tied back.
The WHPA raw gas is sent to Sabratha Platform for treatment.
The PPE treatment plant separates gas from associated condensate/water and the gas is exported directly to Mellitah Onshore Complex.
The separated condensate is partially stabilised and exported directly to shore.
The Sabratha platform is upgraded to handle the new production of Platform A that includes also the installation of a compression module, already planned in the original design phase as future equipment on Sabratha platform.